Bus Maintenance Facility
Status
Bidding Closed
Prebid Date | 8/11/21 2:00pm |
Bid Date | 9/9/21 2:00pm |
Company & Contacts
Location
Napa, CA
4. DESCRIPTION OF WORK: The WORK includes:
• clearing and grubbing,
• demolition ,
• site grading,
• site civil improvements,
• landscaping and irrigation,
• underground utilities,
• new bus wash building structure and MEP,
• new operations building structure and MEP,
• new maintenance building structure and MEP,
• site striping and signage,
• retaining walls,
• drainage structures and storm drain pipes,
• industrial equipment procurement and installation,
• CCTV security system,
• site lighting,
• site perimeter fencing and security access control,
• architectural improvements, and
• Sheehy Court roadway improvements.
ENGINEER’S COST ESTIMATE: The design engineer’s opinion of probable construction cost for this project i approximately $25,000,000.